Rocket Lab announced Wednesday that its Neutron launch vehicle wonât fly until 2027, citing an issue discovered during manufacturing of the rocketâs carbon composite structures.
The announcement was public confirmation of what nearly everyone inside Rocket Lab and the wider space industry already knew. The most recent official update from Rocket Lab in August suggested the company still held hope of delivering the first Neutron rocket to its launch pad at Wallops Island, Virginia, before the end of this year, a schedule that would have almost certainly pushed the first flight into 2027.
But Rocket Labâs statement Wednesday about Neutronâs schedule suggests the company is still struggling with manufacturing the rocketâs large booster stage. Neutronâs reusable first stage is made of carbon composite structures, which offer low weight, high strength, and corrosion resistance. But carbon composites in aerospace are generally harder to manufacture than metallic structures.
Peter Beck, Rocket Labâs founder and CEO, identified a manufacturing defect as the reason for Neutronâs latest schedule slip. The problem lies in the dome sections at the ends of the rocketâs first stage propellant tanks.
âRecently, we identified an issue with the manufacturing process for the propellant domes specifically, and this caused us to delay production and investigate further,â Beck said in a video released by Rocket Lab.
Engineers discovered voids, or air pockets, between layers of carbon fiber that make up the domesâ composite structure. Carbon composite manufacturing involves laying down carbon fiber layers in a mold, then curing, or heating, the material to bind the fibers together. But this is a tricky process, especially for large structures that wonât fit into an autoclave, a high-pressure thermal curing chamber common in modern aerospace factories.
The Neutron rocketâs first stage is the âlargest pressurized structure ever made out of carbon composite,â Beck said. âBecause of its scale, weâve had to develop new out-of-autoclave processes to build Neutron, and this includes custom cure cycles for the very large pieces, like the forward and aft domes for the propellant tanks on Stage One.â
Inspections revealed voids in a newly cured forward dome, defects that could affect the structureâs strength, durability, and reliability, Beck said. âThey donât necessarily mean that the dome would fail in flight, but our practice is to proceed only when we believe the system has the appropriate margins.â
Engineers traced the voids to a recent design change intended to strengthen the rocketâs structure. Rocket Lab introduced the design change after a Neutron propellant tank unexpectedly ruptured during a hydrostatic pressure test in January, a failure blamed on a manufacturing defect at a âcritical joinâ in the tank.
Officials said the failed carbon composite tank was manufactured by a âthird-party contractor using a manual hand-lay process,â a decision made to allow tank testing to move forward while Rocket Lab brought online an automated fiber placement machine, which is now operational. Rocket Lab also deleted joints in the first stage tank structure and increased the thickness of some sections of the carbon composite.
âThose thicker sections are where the voids formed,â Beck said.
Rocket Lab said the problem appears to be solved after modifying the manufacturing process again. An aft propellant dome made with the updated procedure passed inspection.
âWeâve solved the problem,â Beck said. âThat gives us complete confidence to move forward with the new forward dome. That process to make a new forward dome, combining with all the time that it took to investigate, identify, and resolve the issue, has pushed Neutronâs first launch date to next year.â
The Neutron rocket is significantly larger than Rocket Labâs Electron launch vehicle, also made of carbon fiber. The light-class Electron rocket is 3.9 feet (1.2 meters) in diameter, while the medium-lift Neutron measures 23 feet (7 meters) across at its widest.
Rocket Lab completed qualification testing on Neutronâs expendable second stage and payload fairing last year. The rocketâs design is unique: The upper stage and payload rest inside the first stageâs nose cone during the initial phases of launch. A few minutes after liftoff, Neutronâs booster stage will open its clamshell-like nose cone to release the upper stage and payload to continue accelerating into orbit. Then the first stage will close its payload fairing and return to landing on an offshore platform for reuse.
Neutronâs first stage methane and liquid oxygen tanks are the largest elements of the rocket, and they must withstand internal pressure and the rigors of launch and reentry.
Rocket Labâs checklist for the first Neutron flight is long. Final qualification of the first stage is still pending, as is qualification of the rocketâs methane-fueled Archimedes engine, nine of which will power the Neutron booster. Rocket Lab reported in August that it was heading into the âfinal stretchâ of engine qualification testing.
Once that is complete, teams will begin the launch campaign on Virginiaâs Eastern Shore. Launch campaigns for new rockets often take months before a first flight, involving multiple integrated fueling tests, countdown rehearsals, and a static fire.
Engineers often discover new problems during integrated testing, requiring repeat tests and tweaks to procedures and hardware on the launch pad and the rocket. That is the purpose of such testing.
Rocket Lab announced the Neutron rocket in 2021, aiming for a first flight in 2024. The Neutron development timeline has now doubled.
Beck said Wednesday that Neutronâs development remains âon an ambitious timeline.â In previous statements, Beck has emphasized Rocket Labâs focus on quality and its unwillingness to launch an âunproven product.â
âOur aim is to make orbit on the first try,â Beck said last year. âYou wonât see us using some qualifier about us just clearing the pad, and claiming success and whatnot, and that means that we donât want to learn something during Neutronâs first flight that could be learned on the ground during the testing phase.â
Rocket Lab has achieved great success with its Electron rocket, with a capacity of deploying up to 660 pounds (300 kilograms) of payload into a low-altitude orbit. Electron has made 97 flights to date, with 56 consecutive successes.
With Neutron, Rocket Lab seeks to compete for a wider range of launch contracts, eyeing opportunities to sell launches to the US military and operators of satellite megaconstellations. Its lift capability to low-Earth orbit is nearly 29,000 pounds (13,000 kilograms).
âWeâre building the programâs long-term infrastructure at the same time as we build our first rocket, so that we can scale quickly, unlock global launch crunches, and commercial customers, governments, and our own future satellite services are also counting on it,â Beck said Wednesday. âBut Iâve also said that we wonât rush to the pad with unnecessary risk, and that development programs like Neutron have their challenges.â
Neutronâs latest challenge popped up just as the rocketâs prospective customers clamor for more launch capacity. SpaceX, the market leader, is pivoting to the giant Starship rocket and will, in the next few years, retire from commercial service its workhorse Falcon 9 rocket, without which many satellite startups would be unable to put their payloads into orbit affordably.
That puts Rocket Lab in the mix to scoop up business from satellite operators whose payloads donât match up with Starshipâs capabilities. But thereâs stiff competition. Other rocket companies, such as Relativity Space, Stoke Space, and Firefly Aerospace, are working on medium-lift rockets to address the same market.